Thursday, 22 October 2009



The Primary Classrooms are on track for finishing in December. Much of the scaffolding has been removed between the floors and so is starting to look like a real building. We can see the airconditioning ducts being installed at the moment.


The Primary Learning Resource Centre is underway. The ground work has been completed and the slab is being poured. Because of the delays in approval, we are looking at a mib February 2010 completion date at this stage.